Posted by: wrha | July 17, 2015

Saturday 11th July

Sorry for a slightly late report on last weekend.

The main job of the day was to move the Fowler a little further down the stock siding, now the electric pw trolley has gone. This was done using the JCB and it now rests well clear of the Mk1 coach, making access to the Mk1 much easier and safer.
The gas fitter was on site and the cooker in the refurbished buffet is now plumbed in and certified. This makes the kitchen area much easier to use and it certainly looks much tidier.
Peter was busy doing some more work on the drainage system which has worked well during some of the recent monsoon conditions we have all been experiencing this summer.
Work continues on the office container with a start being made on the exterior paintwork, whilst the weather was dry. The refurbished blackboard was mounted inside and will see use as the traction department notice board.
Davie taking advantage of the Fowler move has started work on the front end.
All told a busy day with a number of jobs around the site progressing well.

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: