Work Week 2015 – Monday

The first major task of this works week is to lay a piped drain alongside the bay platform and the access track-work. With a variety of plant either on-site or available good progress was made today. Tony had his little digger at work with the two dumpers running the spoil up to the car park for a job later in the week looking to improve the access path to the platform from the car-park. Whilst the weather held things advanced quite well, with work finally being called to a halt about 5pm when fairly heavy snow set it.
The job will continue tomorrow, hopefully in slightly better weather.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories