Posted by: wrha | November 12, 2012

November Progress

NETWORK RAIL PUBLIC CONSULTATION
.
A series of community drop- in exhibitions is taking place along the route of the northern rebuild, and WRHA committee member Duncan Thomas took himself along to last week’s event in Galashiels. Duncan reports..
.
A good exhibition that had books which showed map sections and satellite images of the complete route. There were a number of  these for people to look at as well as extra copies of the more immediate area around Galashiels and Tweedbank. There was also a projection of an aerial view taken from a fairly low flying helicopter, I would presume of the complete  route, from the Millerhill through to Tweedbank. In discussion with a member of the Network Rail team present he said that they had 85 visitors at the exhibition held at Stow, but that the meeting at Galashiels had been much busier with well over a hundred people through in the first hour of the four that the exhibition was open for. He also said that the vast majority, well over 80% were positive and those who had concerns were mainly about how the railway would impact on people personally, for example how high embankments that need to be re-instated will be. Overall he seemed really pleased with how positive the response of the visitors were. He went on to say that Network Rail should be establishing construction compounds about February time, so from then on there should be a much more visible construction presence along the line.
Overall a seemingly very successful exhibition that  has had an overwhelmingly positive response”

Track Weekend

The last major work weekend of the year has been and gone, and what a great year it was! The weekend’s weather was relatively kind to us: sunshine and showers on Saturday and mist and cold on Sunday. With the painters’ scaffolding having been removed, work concentrated on the stock siding, which is now substantially complete. The final rails were placed into position in the six foot leg, all available sleepers installed and the whole job roughly lined with pinch-bars and good old muscle power. A further load of fifty sleepers will need to be inserted into the siding and headshunt in the spring, following which we’ll undertake some lifting and packing. The laying of concrete sleepered track through the level crossing on the Up line is also pencilled in for the February/ March period, after which we’ll be able to start shuffling our rolling stock into the order we need it.

Drainage installation is now complete on Phase 2a of the running line, with the new cess catchpit in place just north of the platform. This links with the cross drain and six foot catchpit installed way back in 2008, and collects water from the cess on the uphill side of the station as well as the ditches either side of the link path to the car park. The former unsightly “hole” in the banking behind the new catchpit has been backfilled with soil and dressed- off courtesy of Joe, our human JCB.

As usual, work now ramps down as we head into the winter, but things are still happening on site as the weather permits. If you’re planning a trip up to Whitrope, drop us a line on info@wrha.org.uk and we’ll let you know what’s likely to be happening. The site usually shuts down from mid- December through to the beginning of February though.

Once again we offer our sincere thanks to all our volunteers, helpers, supporters and friends who’ve stuck with the project throughout 2012.

Golden Bridge

On running line Phase 2b, Scottish Borders Council have completed the topographical survey of bridge ETC/200 which we commissioned from them earlier in the month, and we now have the completed drawings in our possession. The dimension which really catches your attention is the depth of old ballast: despite having previously removed a decent layer of spoil from the bridge for platform infill, there’s still well over a metre of the stuff before you get to the crown of the arch. The next step is to engage the services of a bridge engineer to analyse the survey data in conjunction with a physical inspection on site, followed we hope with some positive findings going to our landlord, the Forestry Commission.

This slideshow requires JavaScript.

Advertisements

Responses

  1. As the Blogmaster says, 2012 was a fantastic year and I am proud to have played my part. The FIRST passenger trains to run on the Waverley route for over 40 years was a huge success and with 2013 just around the corner I am sure we will build on the success of 2012 and make further progress.

  2. I’m with Tony; it was very satisfying to be able to help return passenger services to the Waverley. I look forward to seeing you all again in 2013 – if not before.

  3. The progress you have made is amazing. Well done (Now the winter is coming, how about posting some of your recent achievements as an update on the main WRHA web site?)


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: